"By utilizing infrared testing, Gaylor Electric was able to save us downtime by preventing a potential shut down before it occurred."

- TOA Manufacturing

TOA Manufacturing

Mooresville, Indiana

E
The project took 16 months to complete and Gaylor Electric invested 18,448 hours. The sheer size of TOA’s facility required a huge amount of electrical installations for the exterior and interior lighting and computer power distribution systems to connect the machinery and robotic instruments.
E
In addition to electrical lighting and power, Gaylor Electric installed numerous specialty systems including a complex telephone scheme that required 60,000 feet of cable, a complete fire alarm system with 60 remote detection and alarm devices, a sophisticated sound/paging layout operating 20 ceiling speakers and 30 wall-mounted horn speakers, security access including card readers, cameras and a monitoring station, and a state-of-the-art video-conferencing for secure communications with offices in Japan.
E
Gaylor Electric completed this complex job with zero OSHA recordables and zero lost time accidents.

Award Winner

Build Type

Design-Assist

Project Size

224,000 SF